The new building is already taking shape. Here, 4 new classrooms are being built on the school's own premises.
The building comprises four classrooms, two smaller rooms used as offices, a storage room and two toilets. The roof was covered, as can be seen on the photo. The Septic Tank, which consists of two chambers, was built.
Next, the plastering of the interior and exterior walls is started and the cement floor is poured. Then it will be decided whether the floor will be tiled or terracotta.
Then the carpenter steps into action again and pulls in the ceiling. The installation of the windows follows. At the same time the frames for the doors must be inserted.
It is realistic that the building will be ready for occupancy at the beginning of the new school year in September 2019 and that the lessons will take place there.